Sunday, 19 January 2014

Jan 20 2014

1. Second floor roofing done
2. frames for doors and windows done

frame for the door-cum-window on first floor

 main door

frames of internal doors and windows


the facade as of now


staircase room from the terrace

Sunday, 12 January 2014

2nd floor master bed room


2nd floor study room


2nd floor kid's room with sitout

view of staircase room from the side


lintel level work progressing: end of dec 2013



front view in december


RCC for terrace




first load of concrete: Jan 8th


Terrace roofing done: Jan 8th 2013